WA Electricity Industry News Summary: March 2021

three black metal electricity posts during golden hour

Alternative approach to energy access in the Goldfields

In a welcome development, Western Power signed up Norton Gold Fields as the first customer in an innovative new scheme that allows large users to access electricity from the SWIS when network capacity is available, while limiting supply when the network becomes congested. The scheme has been implemented without requiring significant upgrades to network infrastructure.

Generator Dispute Resolution Mechanism appointments

The Coordinator of Energy has appointed Generator Arbitrators and a Technical Panel of Experts for the GPS Dispute Resolution Mechanism that recently came into effect on 1 February 2021. There were 4 Arbitrators and 17 experts appointed.

Renewable penetration and minimum demand records for the SWIS

On Thursday 11 March 2021, the SWIS set a record for the share of renewable energy on the grid (at 1.68 GW out of 2.572 GW or ~65% of all generation). Several days later on Sunday 14 March 2021, a minimum demand record of 949 MW was set. This was a cool sunny weekend day where load was naturally low and then exacerbated by high rooftop PV output.

Dampier-to-Bunbury Natural Gas Pipeline (DBNGP) lifespan reduced by 27 years

Australian Gas Infrastructure Group (AGIG), the owners of the pipeline that transports natural gas from the Northwest Shelf to Perth and the southwest has proposed to cut the economic life of the DBNGP by 27 years from 2090 to 2063, citing competition from renewable energy. In its final decision, the ERA has broadly supported the reduction in economic life to 2063 (and the attendant changes to the DBNGP’s depreciation schedule), with a note that it would seek advice from the AEMC for how to deal with assets stranded by policy and technological change.

Estimates for total wholesale electricity costs in the WEM

cutout paper of man examining bills through magnifying glass

As far as we can tell, nobody has published total cost estimates for Western Australia’s Wholesale Electricity Market (WEM).

This is most likely due to the significant (but opaque) role of bilateral contracting in the energy market, which makes up >80% of energy traded in the WEM. Because the details of these contracts are not made public, one can only estimate the cost of bilaterally traded energy.

However, there is enough public data available to make reasonable enough estimates, which is what we’ll attempt to do here.

WEM trading volumes

The table below provides an overview of the volumes of energy traded in the WEM over the past four calendar years, with a breakdown of the proportions traded via bilateral contracts, the day-ahead Short Term Energy Market (STEM) and the real-time balancing market (along with average balancing prices).

Unit2020201920182017
Total consumptionMWh17,460,13317,680,72617,764,74417,189,233
Bilateral contractsMWh14,461,24514,633,33615,883,06216,314,302
Short Term Energy Market (STEM)MWh754,117731,906639,974631,165
Balancing marketMWh2,244,7712,315,4831,241,708243,766
WEM trading volumes (Calendar years 2017-2020) [Source: AEMO Weekly Market Reports]

Of interest are the relative shares of bilateral, STEM and balancing volumes in the total amount of energy traded. While total consumption has remained fairly flat in the last 4 years (fluctuating between 17.2 and 17.8 TWh), the share of bilateral contracts in the total mix has fallen steadily from 95% in 2017 to 83% in 2020. In the meantime, the volume of energy traded on the balancing market has increased its share from 1.4% in 2017 to 12.9% in 2020.

What price to put on bilaterally traded energy?

Bilateral contracts are inherently private transactions where the terms are known only to the counterparties. However, a regulatory scheme imposed by the government after the re-merger of Synergy and Verve Energy in 2014 to mitigate the risk of anti-competitive behaviour (called the Electricity Generation and Retail Corporation Regulatory Scheme) sheds some light on the range of prices one could expect from bilaterally traded energy.

Synergy is required to publish information on its Standard Products, which since 2017 has applied the same Energy Forward Curve to set transfer prices between Synergy’s Generation and Retail arms. Using the Standard Product historical pricing data, the following average annual prices are calculated:

Unit2020201920182017
FLAT BUY$/MWh39.9740.3241.8646.90
FLAT SELL$/MWh48.0150.4052.3258.61
PEAK (*) BUY$/MWh47.3646.5058.4260.01
PEAK (*) SELL$/MWh56.8758.1263.0275.01
Average annual prices for Synergy Standard Products [Source: Synergy Standard Products]

(*) PEAK periods are between 8 am and 10 pm.

The average price for bilateral contracts will most likely fall somewhere between the FLAT BUY and PEAK SELL prices. Taking the midpoint as a rough estimate of the average bilateral price and comparing this estimate to average balancing prices indicate that the prices broadly line up:

Unit2020201920182017
Average bilateral price estimate$/MWh48.4249.2252.4460.95
Average balancing price (volume-weighted)$/MWh53.1948.7150.0562.90
Estimated average bilateral prices vs average balancing prices

Total wholesale market costs

A breakdown of the wholesale cost components in the WEM is shown in the table below:

Unit2020201920182017
Energy
Bilateral contracts$700,219,512720,222,324832,881,314994,377,079
STEM$34,355,63831,876,51630,652,30732,165,531
Balancing market$121,889,981115,512,33467,772,28329,390,553
Capacity
Reserve Capacity
Mechanism
$631,591,475646,626,739606,532,179684,402,090
Ancillary Services
Load Following$56,408,659 (*)72,243,26476,100,79666,335,324
Spinning Reserve$21,867,113 (*)13,049,36418,371,16420,883,843
Load Rejection
Reserve
$1,118,949 (*)930,022852,615946,588
System Restart$2,912,462 (*)2,577,4451,116,098920,674
Dispatch Support$155,046626,314589,355
Market Fees
AEMO$31,250,85529,520,77128,889,48530,565,247
ERA$6,358,4455,290,2584,675,2353,219,978
TOTAL COST$1,607,973,0901,638,004,0841,668,469,7901,863,796,261
Breakdown of total WEM costs (Calendar years 2017-2020) [Sources: see Appendix below]

(*) Ancillary services costs for 2020 are estimated as the latest Ancillary Services Report has not been released at the time of writing.

Note that the table above excludes the following cost components that would also be included in an end-user’s electricity bill:

  • Western Power transmission and distribution network access fees (including metering)
  • Renewable and environmental government policy costs, such as the renewable energy target
  • Electricity retailer (e.g. Synergy) fees

Unit wholesale cost breakdown

Finally, the unit cost breakdown (in $/MWh) can be calculated by dividing total costs by total consumption in the WEM:

Unit2020201920182017
Energy
Bilateral contracts$/MWh40.1040.7346.8857.85
STEM$/MWh1.971.801.731.87
Balancing market$/MWh6.986.533.811.71
Capacity
Reserve Capacity
Mechanism
$/MWh36.1736.5734.1439.82
Ancillary Services
Load Following$/MWh3.234.094.283.86
Spinning Reserve$/MWh1.250.741.031.21
Load Rejection
Reserve
$/MWh0.060.050.050.06
System Restart$/MWh0.170.150.060.05
Dispatch Support$/MWh0.010.040.03
Market Fees
AEMO$/MWh1.791.671.631.78
ERA$/MWh0.360.300.260.19
TOTAL COST$/MWh92.0992.6493.92108.43
Breakdown of unit wholesale costs in the WEM (Calendar years 2017-2020)

Appendix: Data sources

Data CategoryDescriptionSource
EnergyWEM Weekly Market ReportAEMO
EnergyHistorical Standard Product PricesSynergy
Reserve CapacityHistorical Reserve Capacity PricesAEMO
Reserve CapacityCapacity Credits Assigned Since Market StartAEMO
Ancillary ServicesWEM Ancillary Services ReportsAEMO
Ancillary ServicesAncillary Service Requirements Decision 2019/20ERA
Ancillary ServicesAncillary Service Parameters Determination 2020/21ERA
Market FeesWEM Market Accounting ReportsAEMO
Data sources used to develop the wholesale cost estimates

WA Electricity Industry News Summary: February 2021

white lantern lot

WA State Liberal and Labor energy plans

The Labor and Liberal parties announced their energy plans ahead of the state election in March. Zak Kirkup surprised everyone with an aggressive decarbonisation plan that included the closure of Muja and Collie coal-fired power stations by 2025 and net-zero emissions by the state government by 2030. The ambitious plan was deemed “unachievable” by the Labor government, which promised a more sober decarbonisation plan (net-zero emissions for the whole state by 2050), while promising $259m to build 1,000 solar, battery and hydrogen standalone power systems.

Energy minister Bill Johnston debated the Liberals’ David Honey and The Greens’ Tim Clifford at an industry event on 16 February 2021, where Johnston described the Liberals’ plan as “costly and unrealistic”.

Western Power Standalone Power Systems

The Electricity Corporations (Electricity Generation and Retail Corporation Area of Operation) Regulations were amended to allow Western Power to provide standalone power systems (SPS) within its distribution license service area as an alternative to network augmentations / replacements.

Western Power then deployed a SPS on two properties left without power after the Wooroloo bushfires, while being able to remove 2km of distribution lines to the properties. This marks the first time an SPS has been installed in the Greater Perth metro area.

PowerBank community battery trial extended

Western Power and Synergy’s community battery trial (PowerBank) has been extended to nine communities in metropolitan Perth and regional WA. The trial will allow household participants to access a community battery and “bank” excess solar from their rooftop PV systems for deferred use in the evenings (with a cost of $1.20 or $1.40 a day for 6 kWh or 8 kWh of storage respectively).

Launch of Virtual Power Plant trial Project Symphony

The WA government announced the launch of a $35m virtual power plant trial dubbed Project Symphony. The trial, which is being jointly implemented by AEMO, Energy Policy WA, Synergy and Western Power, will coordinate rooftop PV, batteries and loads from 500 homes and businesses in the Southern River area.

Merredin Solar Farm secures PPA with BHP Nickel West Kwinana

BHP Nickel West Kwinana refinery has signed a 10-year Power Purchase Agreement (PPA) starting from 1 February 2021 with the 100 MWac Merredin solar farm, WA’s largest and newest solar farm owned by Chinese solar panel maker Risen Energy. The value of the bundled PPA (energy and renewable energy certificates) was not disclosed, but WEM balancing price submissions for MERSOLAR indicate an all-in price around $50/MWh.

AEMC ruling on DER Technical Standards

On 25 February 2021, the AEMC made a final determination on the establishment of DER Technical Standards to allow AEMO and DNSPs to better manage the increasing penetration of rooftop PV in the system. The DER Technical Standards will include the requirements set out in the newly updated AS 4777.2:2020. The rule will commence on 18 December 2021 and only apply to new or altered connections in the NEM. At this stage, it isn’t clear whether the same standards will be adopted in Western Australia.

Parmelia Gas Pipeline converted to be “hydrogen-ready”

APA Group announced a pilot project to convert a 43 km section of the 416 km long Parmelia Gas Pipeline to be hydrogen-ready (either blended with natural gas or as pure hydrogen). The Parmelia Gas Pipeline currently transports natural gas from Dongara to Pinjarra, with laterals to the Perth metro area and Kwinana. This would open the door for the transport of green hydrogen from the WA government’s proposed green hydrogen mega-project site at Oakagee (13km north of Geraldton).

Rooftop PV Capacity in the SWIS – January 2021 Edition

black solar panels on brown roof

Now that 2020 is finally behind us, let’s dig into the data and pull out the latest estimates for rooftop PV capacity in the South West Interconnected System (SWIS), Western Australia’s largest electricity grid.

Here are the headline numbers:

Rooftop PV Capacity (MWp)01/01/202001/01/2021Change
Total small-scale capacity1,281.21,576.6295.4
Total large-scale (>100 kW) capacity25.429.23.8
Total rooftop PV capacity1,306.61,605.8299.2

Despite COVID-19, there was robust growth in small-scale (mainly residential) rooftop PV installations in 2020, with over 295 MW installed compared with 240 MW in 2019 (a 23% year-over-year growth).

Meanwhile, large-scale installations slowed down significantly from 13.1 MW in 2019 to just 3.8 MW in 2020.

The aggregate rooftop PV capacity of 1,605.8 MW has now overtaken the combined capacity of the coal-fired power stations in the SWIS (Bluewaters, Collie and Muja C/D have a combined maximum capacity of 1,566.9 MW).

The cumulative rooftop PV capacity in the SWIS since 2007 is shown in the graph below:

As can be seen from the graph above, rooftop PV capacity growth has accelerated in the past few years. It remains to be seen whether installations will continue to grow at the same pace with the reduction in the feed-in tariff in November 2020. The answers to the following questions will likely determine whether there will be continued growth or saturation in the demand for new rooftop PV systems:

  • How sensitive are prospective buyers to the implied investment returns / payback period on new PV systems?
  • Will owners of older existing systems with expired grandfathered feed-in tariffs begin to upgrade to larger systems?
  • Will there be an uptake in battery energy storage systems to take advantage of falling prices and higher feed-in tariffs during peak times?
  • Will new housing developments / construction include rooftop PV as a standard feature?
  • Will an uptake in electric vehicle purchases incentivise owners to install larger rooftop PV systems for charging (and possible vehicle-to-grid) purposes?

Data sources and notes

All of the data used in this analysis is sourced from the Clean Energy Regulator (CER) website:

The postcode data for small- and large-scale installations is filtered for postcodes in the SWIS. Large-scale ground-mounted installations are also removed from the data set (e.g. Merredin solar farm or Greenough River solar farm). The coarseness of the postcodes at the edges of the SWIS may introduce some error into the statistics, but the volume of installations in these areas are small relative to the total number of installations.

The small-scale postcode data was extracted on 25 January 2021, and it appears that the data set for December 2020 is not yet fully complete (showing only 2,295 installations for December 2020 compared with a monthly average of 3,759 installations over the period from January 2020 to November 2020). That said, the reduced volumes could potentially reflect softening demand after the REBS scheme was replaced by the DEBS scheme and the tariff reduced to $0.03/kWh during the day after 6 November 2020 (though such a sharp drop-off seems unlikely).

Note that the quoted dates are actually accreditation dates, which may not necessarily line up with the actual installation dates. This is more of an issue with the large-scale installations (>100 kW). For example, a rooftop PV system is installed and it may be months before the proponent applies for accreditation.

Diagnosing Load Flow Convergence Issues

Load flow studies form the basis for the steady-state analysis of power systems and are performed for a wide range of applications from planning to operations. The studies are typically conducted using computer software packages such as PSSE, DIgSILENT PowerFactory, ETAP, PowerWorld and SKM Power*Tools.

The load flow (or power flow) calculation solves for four steady-state electrical quantities (at each bus and branch element):

  • Voltage V at each bus
  • Phase angle Φ at each bus
  • Active power flow P through each branch element
  • Reactive power flow Q through each branch element

We can use these four basic electrical quantities to calculate other quantities of interest, for example:

  • Apparent power S through each branch element
  • Current I flowing through each branch element
  • Loading of branch elements (e.g. transformers, cables, etc) based on continuous and short-term equipment ratings
  • Voltage drop between buses
  • Total system load
  • Total amount of generation dispatched
  • Network losses

These calculated quantities are of interest to electrical network operators and design engineers in order to ensure that the power system operates efficiently and within limits. The rest of this article will talk about the generic structure of a commercial power flow solver / algorithm and how to debug convergence problems.

Algorithm Structure

Power flow solution algorithms are typically comprised of inner and outer loops:

  • The inner loop calculates the main iterations of the solver (e.g. Newton-Raphson, Gauss-Seidel, etc) in order to minimise the power (or current) mismatch equations.
  • The outer loop is used to check and satisfy control conditions (e.g. auto tap changer / shunt control) and limiting behaviour (e.g. generator reactive power limits).

Note that automatic tap or shunt control is sometimes included in the inner loop, but only when continuous tap/shunt steps are used. When automatic tap and shunt control is incorporated in the outer loop, the power flow algorithm will attempt to switch the positions of the taps and shunts at the end of every inner loop iteration to satisfy the control conditions (e.g. bus voltage or branch power flow setpoints).

Diagnosing Convergence Issues

When a load flow fails to converge, the first step to diagnosing the problem is to identify whether the algorithm has failed in the inner or outer loop.

An inner loop problem signifies that the Newton-Raphson equations could not be solved, which could be due to ill-conditioning, voltage stability issues, etc. This usually results in a program error message stating that the algorithm has either diverged or stagnated.

Inner loop problem (from DIgSILENT PowerFactory)

On the other hand, when the problem is in the outer loop, the Newton-Raphson equations can be solved, but control conditions can’t be met (e.g. voltage setpoint could not be reached with transformer taps at maximum / minimum settings or are hunting between two tap steps). Typically, a maximum number of outer loop iterations must be reached before an error is reported by the program.

Outer loop problem (from DIgSILENT PowerFactory)

Tackling Inner Loop Problems

As mentioned earlier, inner loop problems suggest that the system is ill-conditioned and the Newton-Raphson algorithm either diverges or is stuck in a local minimum (i.e. stagnated). Mismatches in generation, poor distribution of generator dispatch and local voltage stability issues are among the common causes for an inner loop problem:

  • Mismatches in generation and load: when there is a large mismatch in generation and load (i.e. over- or under-generation), the discrepancy in active power has to be supplied or absorbed by the slack element. Depending on the location of the slack element, this can lead to large power flows from one part of the network to another, which can cause imbalances in the voltage profile and lead to convergence problems.
  • Distribution of generator dispatch: similar to mismatches in generation, poor distribution of dispatched generation can lead to large unwanted power flows from one part of the network to another.
  • Local voltage stability: relates to busbars reaching the nose point of the PV curve (voltage collapse). This could be very localised due to large loads placed at weak radial parts of the network without sufficient reactive compensation, or could affect larger areas where multiple buses have depressed voltages.

Some approaches to resolving inner loop problems are as follows:

  • Turn off enforce reactive power limits option: most programs have an option to limit the reactive power output of PV buses (generators, SVCs, etc) so that they are within their reactive power capability curves. When a PV bus reaches limits, it is converted to a PQ bus in the outer loop with the reactive power set to its limits and the inner loop is run again, which can then fail due to voltage stability reasons (i.e. the PV bus is supporting the local voltage, but with limits enforced, voltages can go wild). Turning this option off can help diagnose which generators, SVCs, etc are supplying / absorbing large amounts of reactive power and their associated problem buses.
  • Change the location of the slack element and distribute generator dispatch: so that there are more balanced flows through the network. Some programs have a distributed slack bus option that automatically caters for mismatches in generation by distributing the slack across all in-service generators according to their nominal ratings.
  • Switch in or add shunt compensation: in order to support weak buses that may have voltage stability problems.

Tackling Outer Loop Problems

Outer loop problems are normally associated with voltage control issues from the following elements:

  • Generators – reaching their reactive power capability limits
  • SVCs – reaching their reactive power capability limits
  • Transformer automatic tap changers – reaching maximum tap settings without satisfying voltage setpoint tolerances
  • Shunt controllers – reaching maximum shunt steps without satisfying voltage setpoint tolerances

Some approaches to resolving outer loop problems are as follows:

  • Increase the maximum number of outer loop iterations: particularly for larger systems, the outer loop solution may take many iterations.
  • Change voltage control setpoints and tolerances: the bus voltage setpoints and tolerances can be adjusted to help the solution along.
  • Lock taps and/or shunts: automatic transformer tap and shunt adjustment options can be de-selected to lock the taps and shunts at their initial positions.
  • Reset taps and/or shunts: the initial tap and shunt positions may not be well configured for the particular scenario. Reset tap positions by setting all transformers to neutral tap and re-configure initial shunt positions to better control system voltages (e.g. if you know that a bus has a low voltage, put some capacitors in service).